Conveyor gallery steel structures fail at the fabrication-to-assembly transition, not at the design stage. The real risk isn't load calculations or span optimization—it's whether your 60-meter gallery can physically be transported, unloaded, bolted together, and welded in sequence without field modifications. Most engineering teams treat galleries as continuous frames. We see them as segmented puzzles where every piece must fit transport limits, crane reach, bolt access, and welder positions. If your design doesn't answer "how does this get assembled in the field?" before we cut the first plate, you're managing a rework project, not a construction project.
Here's what actually determines whether your conveyor gallery works: not the structural calculations your consultant sends us, but whether the person with the wrench can physically access the bolt—and whether the person with the welding rod can reach the splice without building a scaffolding city around it.
Your structural engineer drew a beautiful 60-meter continuous frame. It looks clean on the drawings. It probably passes every load check. But it can't leave our factory.
Transport limits control segment length, not structural logic. The longest trailer-transportable segment in most regions is 12–15 meters.[^1] If your gallery design doesn't show pre-planned splice locations that respect this limit, the fabricator will segment it for you—and those cuts won't match your connection logic.
A 60-meter gallery needs 4–5 field splices if each segment maxes out at 12 meters. But most designs we receive show splice locations at 20-meter intervals—because that's where the structural grid falls. When we ask "how should we transport this?" the answer is usually "can't you just weld it longer?" No. We can't put a 20-meter truss on a 15-meter trailer.
So we re-segment the gallery. We add splices at 11-meter marks to fit transport. Those new splices land in the middle of panel points, halfway between columns, sometimes right through a bracing connection. Now we're splicing main chords where there's no logical connection plate, creating field joints that have six bolts instead of twelve because there's no room for a proper flange.
| Constraint Type | Typical Limit | What This Means for Your Design |
|---|---|---|
| Trailer bed length | 12–15 meters | Maximum continuous segment length |
| Road width limits | 3.5–4 meters | Maximum assembled width including bracing |
| Height restrictions | 4.5 meters | Maximum truss depth with transport clearance |
| Weight per axle | 20–25 tons | Affects whether segments can include pre-attached pipe supports |
| Turning radius | 15–20 meters | Limits single-piece trusses with complex geometries |
We once had a 72-meter gallery designed with splices every 24 meters—three segments total. Beautiful on paper. We had to re-segment into six pieces. The client ended up with twice as many field splices as the original design, all added in locations where there were no connection plates, no bolt patterns, no welding prep details. That project burned three extra weeks just negotiating who pays for the redesign.
If you're specifying a conveyor gallery, the first question isn't "what's the optimal span?" It's "where can we put splices that allow 12-meter segments AND land on logical connection points?"
Transport limits are one thing. Site access is another. I've seen projects where the trailer route to the site included a 90-degree turn through a gate that was only 4 meters wide. The gallery segments were 4.2 meters wide with bracing attached. The truck couldn't make the turn. We had to send the bracing loose, then bolt it on-site—adding 40 extra field connections that weren't in anyone's budget or schedule.
Another project had a bridge with a 30-ton weight limit. Our segments were 28 tons each—just under the limit—but the client's crane was on the other side of the bridge. We ended up unloading segments at a staging area 2 kilometers away, then using a smaller crane to move them piece by piece across the bridge. Added two weeks.
Here's the sentence I hear most often when a gallery arrives on site: "There's no way to reach that bolt." The second most common: "If I weld this joint first, I can't access the other joint."
Nodes connect columns, beams, bracing, and pipe supports in one location. If the design stacks all these connections at the same elevation with no offset, there's physically no room for a wrench, a welding torch, or an inspector's hand. Good designs separate connection points by 200–300mm vertically or horizontally so each joint can be completed in sequence.[^2]
Last year we fabricated a 4,200-ton gallery for a coal chemical project. The design showed column splices at 6-meter intervals with two rows of M24 bolts—sixteen bolts per connection. But the bracing connections landed 250mm below each column splice, at the same elevation as the lower bolt row.
The ironworker needs to torque the column splice bolts. But the bracing gusset plate covers half the bolt heads. So you have two choices: install the bracing first, then try to reach around the gusset to torque the column bolts (impossible with a torque wrench). Or install the column splice first, then discover you can't fit the bracing bolts because the column splice plates block access.
We flagged this during shop drawing review. The client's response: "Just make it work." We made it work by shimming the bracing gusset 50mm outward with spacer plates—adding material and welding that wasn't in the design. The ironworkers spent an extra four hours per node just sequencing the bolts. That's 60 nodes across the gallery. 240 extra man-hours for a problem that could've been solved by moving the bracing connection 300mm higher or lower on the drawing.
Process designers place pipe routes. Structural designers add pipe supports to hold those pipes. But nobody asks: "Can a person physically bolt this support bracket to the beam while standing on a ladder?"
Standard mistake: pipe supports welded to the bottom flange of a main beam, 8 meters above ground, with the bolt pattern facing downward. The ironworker is on a ladder, reaching overhead, trying to hold a 40-kilogram support bracket in place with one hand while starting bolts with the other hand. It's not happening.
Here's what works better:
Most conveyor gallery designs start with structural logic: "Let's use 8-meter spans because that's efficient for beam sizing." Then the process team adds piping and discovers there's no room between columns for the pipe bends. Or the cable trays interfere with the bracing.
The correct design sequence is: define pipe routes and equipment loads first, then design the structure around those constraints. If you design the frame first and add piping later, you're designing twice.
We built a gallery for a refining project where the structural drawings showed clean 6-meter column spacing. The piping drawings arrived six weeks later showing three parallel pipe runs, including one 600mm line with a 90-degree bend every 24 meters.
Problem: the bend radius for a 600mm pipe is about 2.4 meters. The column spacing was 6 meters. The bends landed directly in line with the columns. You can't route a 2.4-meter pipe bend through a 300mm-wide column. So the process team moved the bend locations 1 meter to one side. Now the pipe run was off-center relative to the structural grid. The structural loads shifted. The column bases needed redesign because the eccentric load changed the moment reactions.
If the structural designer had seen the pipe routing before finalizing column locations, they could've offset the grid by 1 meter or adjusted the span to 7 meters in that section. Instead, we got drawings that physically didn't fit together, and both teams blamed each other while the schedule burned two months in revision cycles.
If you're specifying a conveyor gallery and you want to avoid this mess, here's the checklist we wish clients would work through before releasing structural drawings:
Field splices are where theory meets reality. On paper, you can splice anywhere—just add a connection plate and some bolts. In practice, every splice needs four things: bolt access, welding position, QC inspection space, and alignment tolerance.
Field splices should land at column centerlines or mid-span of beams—never 300mm away from another connection.[^4] The welding position should be flat or horizontal, never overhead unless absolutely unavoidable. Inspection access should allow 500mm clear space around the joint for UT probes and magnetic particle testing.
We had a gallery project where the designer placed column splices 2 meters above the foundation level. But the columns were box sections, 400mm × 400mm. The splice required full-penetration welds on all four sides. Two sides were accessible from ladders—no problem. The other two sides faced inward toward the gallery centerline. To weld those sides, the welder had to work overhead, reaching between the column and the nearest bracing member, with 300mm of clearance.
We ended up building temporary scaffolding around every column just to give the welders a stable platform. The scaffolding cost $12,000. The welding took three times longer than it should have because the welders couldn't hold a steady arc angle in that position. And the UT inspection failed twice because the inspector couldn't get the probe aligned properly with such limited access.
| Welding Position | Description | Field Feasibility |
|---|---|---|
| Flat (1G) | Weld bead is horizontal, welder works from above | Best—fast, high quality, minimal defects |
| Horizontal (2G) | Weld bead is horizontal, welder works from the side | Good—slower than flat, but stable and accessible |
| Vertical (3G) | Weld bead is vertical, welder works facing the joint | Acceptable—requires skill, but common in field splicing |
| Overhead (4G) | Weld bead is horizontal, welder works from below | Avoid unless no alternative—slow, high defect rate, safety risk |
If your splice design forces overhead welding, you're adding cost and risk. For example: column splices. If you place the splice 2 meters above grade, the column is already standing when the splice is welded—which means the top flange is overhead for the welder. If you place the splice at grade level, the bottom segment can be welded flat on sawhorses before the column is erected, then the top segment is horizontal after erection. Same connection, completely different welding position, half the labor cost.
Most NDT methods require the inspector to place a probe, transducer, or magnetic particle testing pad directly on the weld surface. If there's a bracing member 200mm away, they can't do it.
Standard clearance requirements:
We had a splice design where the gusset plate for the bracing was welded 150mm from the column splice. The UT inspector couldn't fit the probe between the gusset and the splice flange. We had to cut access holes in the gusset plate, do the inspection, then plug-weld the holes closed afterward. Added two days per splice.
I'm not talking about calculation errors or load mistakes. I'm talking about coordination failures—where every individual drawing is correct, but they don't fit together when you overlay them.
The most common coordination failure is when structural drawings, piping drawings, and electrical drawings are developed in parallel with no spatial clash checking. The structure gets built, then the piping team discovers their pipes run through the bracing. Or the electrical team discovers the cable tray is blocked by a stiffener plate.
This happened on a 5,000-ton project we completed two years ago. The structural package showed diagonal bracing in every bay—classic X-bracing pattern. The piping package showed a 500mm steam line running horizontally through the center of each bay. The bracing and the pipe occupied the same space.
A 500mm pipe with 50mm insulation has a total diameter of 600mm. It needs at least 700mm of vertical clearance to account for support brackets and expansion loops. The bracing runs diagonally through that space. You can't "route around" a diagonal brace without changing the pipe elevation by 2 meters or more—which throws off the whole piping system.
The only reliable way is 3D coordination before you release fabrication drawings. I mean actual 3D modeling where you overlay structural steel, piping, electrical, HVAC, and equipment in one model and check for interferences.
The clash detection process should happen like this:
The most expensive four words in construction are "we'll figure it out later." Because "later" means the steel is already fabricated. The pipe spools are already on-site. The crew is standing around waiting for someone to decide whether to cut the bracing or reroute the pipe, and every day of delay costs $15,000 in idle labor and equipment rental.
We fabricated a gallery where the electrical drawings were released two months after the structural drawings. The cable tray routing wasn't finalized yet, so the structural designer just left "allowance space" for electrical—a 1-meter-wide zone marked "no structure here."
The electrical designer placed the cable tray in that zone. Good so far. But they also added junction boxes every 20 meters for circuit connections. The junction boxes were 600mm × 600mm × 300mm, and they had to be bolted to something structural. The "allowance space" had no structure in it—that was the whole point.
We added the brackets. But now the brackets extended into the "no structure" zone. And the junction boxes extended 300mm beyond the brackets. And the whole assembly shifted the cable tray 200mm off-center, which meant it now interfered with the pipe supports that were welded to the beams.
This cascade of changes burned six weeks and $40,000 in rework—because nobody coordinated electrical equipment dimensions with structural support locations during design.
Typical conveyor gallery spans range from 6 to 12 meters between columns[^5], depending on loads and design codes. But the "maximum" span isn't determined by structural capacity—it's determined by fabrication and transport limits. Longer spans require deeper trusses, which increase transport height and reduce road clearance.
Count the total gallery length, divide by the maximum transportable segment length (usually 12 meters), then round up. A 72-meter gallery needs at least six segments. But the actual number of splices depends on where you can logically place connections—ideally at column centerlines or mid-span points, not in the middle of a panel.
For industrial projects, field splices typically follow AWS D1.1 (Structural Welding Code—Steel) or EN 1090 depending on the project location[^6]. The specific weld type—full-penetration groove weld, partial-penetration, or fillet weld—depends on the joint loading and design requirements.
Only if the gallery length is under 12 meters and the width plus bracing doesn't exceed 4 meters. Anything larger must be segmented. Some fabricators offer modular sub-assemblies—like pre-welded truss sections with bolted field splices—which reduces site welding but still requires segment shipping.
For a 3,000–5,000-ton gallery, fabrication typically takes 10–14 weeks after shop drawing approval, depending on the complexity of connections and the number of segments. This assumes normal production scheduling with no material delays.
Conveyor gallery steel structures fail or succeed based on decisions made before the first plate is cut. If your design treats the gallery as a continuous frame without thinking about segment transport, field splice locations, node assembly sequences, and piping coordination, you're setting up a rework project.
The question you need to answer during design isn't "does this structure meet load requirements?" It's "can this structure be fabricated in segments that fit on trucks, assembled by workers with wrenches, welded in positions that don't require scaffolding cities, and inspected without cutting access holes?"
We've fabricated over 50,000 tons of conveyor galleries at MEICHEN STEEL STRUCTURE. The projects that finish on time and on budget are the ones where the client's engineering team asked us "where should the splices go?" before finalizing the design—not after. If you're specifying a conveyor gallery for a petrochemical or mining project, talk to your fabricator early. Show them the pipe routing. Walk through the erection sequence. Let them flag the node connections that won't work before you commit to steel procurement.
That conversation might add two weeks to your design phase. But it'll save you two months on-site. Contact us at info@meichensteel.com if you want to review your gallery design before it becomes a field problem.
Steel Structure Workshop Solutions
Steel Warehouse Solutions
Heavy Steel Structures for Equipment
Indonesia North Kalimantan Aluminum Plant Project
Steel Structure Factory and Warehouse Project for a Material Processing Production Base
Luoyang Haode Auto Parts Steel Structure Factory Project
Automated Glass Production Line Steel Structure Factory Building Project
Oil & Gas Modular Steel Structure Fabrication Project